Construction Progress

Q4 2027 Estimated Completion Date

6.79 %
  • May

    2026

Foundation Works Progressing

Raft foundation and basement structural elements have been completed in key areas, while additional foundation works continue across the development. Excavation and shoring have been fully completed, with the official completion certification secured.

  • April

    2026

Substructure works advancing

Excavation has been completed to final formation levels across most areas, with tower crane and pit zone enabling works established. Foundation activities are now progressing, including raft thickenings, sump pits, and tower crane foundations, marking a key construction milestone.

3.36%
2.18 %
  • March

    2026

Stability Achieved, Progress Ongoing

Shoring, anchoring, and micro piling are now fully completed.
Excavation has progressed significantly, with dewatering works ongoing to maintain site stability.

  • February

    2026

Groundworks in Progress

Shoring works are now complete. Excavation is currently underway, alongside ongoing anchoring and guniting activities to secure and stabilize the site, preparing the ground for the next phases of foundation works.

1.03%
0.62 %
  • January

    2026

Shoring Works Completed

Securing the excavation area and stabilizing the site for safe progress. This milestone sets the ground for the next stages of foundation and structural works.

  • May

    2026

Foundation Works Progressing

Raft foundation and basement structural elements have been completed in key areas, while additional foundation works continue across the development. Excavation and shoring have been fully completed, with the official completion certification secured.

6.79%
  • April

    2026

Substructure works advancing

Excavation has been completed to final formation levels across most areas, with tower crane and pit zone enabling works established. Foundation activities are now progressing, including raft thickenings, sump pits, and tower crane foundations, marking a key construction milestone.

3.36%
  • March

    2026

Stability Achieved, Progress Ongoing

Shoring, anchoring, and micro piling are now fully completed.
Excavation has progressed significantly, with dewatering works ongoing to maintain site stability.

2.18%
  • February

    2026

Groundworks in Progress

Shoring works are now complete. Excavation is currently underway, alongside ongoing anchoring and guniting activities to secure and stabilize the site, preparing the ground for the next phases of foundation works.

1.03%
  • January

    2026

Shoring Works Completed

Securing the excavation area and stabilizing the site for safe progress. This milestone sets the ground for the next stages of foundation and structural works.

0.62%