-
-
June
2026
Basement Structure Taking Shape
Construction continues to advance at a strong pace, with the successful casting completion of the first Basement 1 slab, marking another significant milestone in the project's evolution. The final raft foundation is now prepared for concrete casting, while Tower Crane 2 has been fully erected and is in the final stages of commissioning, further enhancing the project's readiness for the next phase of structural works. Each milestone brings the vision closer to reality, driven by exceptional craftsmanship, engineering excellence, and an uncompromising commitment to quality.
-
-
May
2026
Foundation Works Progressing
Raft foundation and basement structural elements have been completed in key areas, while additional foundation works continue across the development. Excavation and shoring have been fully completed, with the official completion certification secured.
-
-
April
2026
Substructure works advancing
Excavation has been completed to final formation levels across most areas, with tower crane and pit zone enabling works established. Foundation activities are now progressing, including raft thickenings, sump pits, and tower crane foundations, marking a key construction milestone.
-
-
March
2026
Stability Achieved, Progress Ongoing
Shoring, anchoring, and micro piling are now fully completed.
Excavation has progressed significantly, with dewatering works ongoing to maintain site stability.
-
-
February
2026
Groundworks in Progress
Shoring works are now complete. Excavation is currently underway, alongside ongoing anchoring and guniting activities to secure and stabilize the site, preparing the ground for the next phases of foundation works.
-
-
January
2026
Shoring Works Completed
Securing the excavation area and stabilizing the site for safe progress. This milestone sets the ground for the next stages of foundation and structural works.
-
June
2026
Basement Structure Taking Shape
Construction continues to advance at a strong pace, with the successful casting completion of the first Basement 1 slab, marking another significant milestone in the project's evolution. The final raft foundation is now prepared for concrete casting, while Tower Crane 2 has been fully erected and is in the final stages of commissioning, further enhancing the project's readiness for the next phase of structural works. Each milestone brings the vision closer to reality, driven by exceptional craftsmanship, engineering excellence, and an uncompromising commitment to quality.
-
May
2026
Foundation Works Progressing
Raft foundation and basement structural elements have been completed in key areas, while additional foundation works continue across the development. Excavation and shoring have been fully completed, with the official completion certification secured.
-
April
2026
Substructure works advancing
Excavation has been completed to final formation levels across most areas, with tower crane and pit zone enabling works established. Foundation activities are now progressing, including raft thickenings, sump pits, and tower crane foundations, marking a key construction milestone.
-
March
2026
Stability Achieved, Progress Ongoing
Shoring, anchoring, and micro piling are now fully completed.
Excavation has progressed significantly, with dewatering works ongoing to maintain site stability.
-
February
2026
Groundworks in Progress
Shoring works are now complete. Excavation is currently underway, alongside ongoing anchoring and guniting activities to secure and stabilize the site, preparing the ground for the next phases of foundation works.
-
January
2026
Shoring Works Completed
Securing the excavation area and stabilizing the site for safe progress. This milestone sets the ground for the next stages of foundation and structural works.