Construction Progress

Q4 2027 Estimated Completion Date

2.33 %
  • June

    2026

Foundation Works Progressing Steadily

The project continues to demonstrate steady advancement, with piling works substantially completed and pile head preparation progressing across the site. Excavation activities are ongoing, alongside continued capping beam works. In parallel, tie-back anchoring, installation of precast shoring panels, and dewatering infrastructure works are actively progressing, further strengthening site stability and supporting the continued progression of foundation development.

  • May

    2026

Groundworks gaining momentum

Piling works continue to advance across the project, with a significant portion of the scope completed. Excavation activities and capping beam works are now underway, supporting the next phase of foundation construction.

1.42%
1.03 %
  • April

    2026

Enabling works progressing on site

Guide wall works for the secant piling system have been completed across both front and rear zones, with secant piling activities continuing to progress steadily on site. Hard pile steel cage installation, along with soft pile drilling and concrete casting, has been successfully completed within the left-side zone.

  • June

    2026

Foundation Works Progressing Steadily

The project continues to demonstrate steady advancement, with piling works substantially completed and pile head preparation progressing across the site. Excavation activities are ongoing, alongside continued capping beam works. In parallel, tie-back anchoring, installation of precast shoring panels, and dewatering infrastructure works are actively progressing, further strengthening site stability and supporting the continued progression of foundation development.

2.33%
  • May

    2026

Groundworks gaining momentum

Piling works continue to advance across the project, with a significant portion of the scope completed. Excavation activities and capping beam works are now underway, supporting the next phase of foundation construction.

1.42%
  • April

    2026

Enabling works progressing on site

Guide wall works for the secant piling system have been completed across both front and rear zones, with secant piling activities continuing to progress steadily on site. Hard pile steel cage installation, along with soft pile drilling and concrete casting, has been successfully completed within the left-side zone.

1.03%