June
2026
Foundation Works Progressing Steadily
The project continues to demonstrate steady advancement, with piling works substantially completed and pile head preparation progressing across the site. Excavation activities are ongoing, alongside continued capping beam works. In parallel, tie-back anchoring, installation of precast shoring panels, and dewatering infrastructure works are actively progressing, further strengthening site stability and supporting the continued progression of foundation development.
-
-
May
2026
Groundworks gaining momentum
Piling works continue to advance across the project, with a significant portion of the scope completed. Excavation activities and capping beam works are now underway, supporting the next phase of foundation construction.
-
-
April
2026
Enabling works progressing on site
Guide wall works for the secant piling system have been completed across both front and rear zones, with secant piling activities continuing to progress steadily on site. Hard pile steel cage installation, along with soft pile drilling and concrete casting, has been successfully completed within the left-side zone.
-
June
2026
Foundation Works Progressing Steadily
The project continues to demonstrate steady advancement, with piling works substantially completed and pile head preparation progressing across the site. Excavation activities are ongoing, alongside continued capping beam works. In parallel, tie-back anchoring, installation of precast shoring panels, and dewatering infrastructure works are actively progressing, further strengthening site stability and supporting the continued progression of foundation development.
-
May
2026
Groundworks gaining momentum
Piling works continue to advance across the project, with a significant portion of the scope completed. Excavation activities and capping beam works are now underway, supporting the next phase of foundation construction.
-
April
2026
Enabling works progressing on site
Guide wall works for the secant piling system have been completed across both front and rear zones, with secant piling activities continuing to progress steadily on site. Hard pile steel cage installation, along with soft pile drilling and concrete casting, has been successfully completed within the left-side zone.